There will be lots of construction happening this summer, which will impact access to our buildings and facilities as well as summer programming locations. Starting June 3rd we will have construction crews in our community working on the following projects:

  • Independence Elementary STEM School: Phase II renovations (HVAC and Media center update)
  • Liberty Elementary School: Media center renovation, parking lot redesign
  • High School: Parking lot additions
  • County Road 43 Reconstruction: Resurfacing, utilities updates and intersection redesign (installation of mini roundabout at Glenwood Ave and County Rd 43)

Maps showing the areas of impact and closures can be found below, click each map to enlarge).

If you need to access our buildings this summer for summer programming, please refer to the list below.

Summer Programming Locations

Independence Elementary STEM:

Middle School:

  • Kid's Club & Hive Time Childcare (Enter Door B)
  • Summer Food Service (Enter Door A)
  • Summer Odyssey (Enter Door A)
  • ESY (Enter Door E, East end back of building)

High School: 

  • Community Education Enrichment/Recreation Classes (Enter Door A)
  • Fitness Center (Enter Door N)
County Road 43 will be closed from 203rd Avenue to Park Avenue. The liberty site will only be accessible via 172nd Street (east of town on US 10)
Driveway on West end of building (Auditorium side) will be closed June 3-Aug 18.
Map Indicating Access to Liberty Elementary. The main parking lot will be closed/limit access. There will be field access through the east entrance.