- 2021 Bond Referendum -copy 2

Renew and Restore our School Facilities
-
On November 2, 2021, our community made a historic decision to restore and renew our district facilities! The passage of this $30 million bond referendum will allow us to enact a plan to restore and renew our school facilities for future generations while maintaining fiscal responsibility for our tax payers.
We are currently working towards completion of these projects. Our goal is to have everything complete by 2025.
In the interest of transparency, we will be updating this site regularly with timelines of the projects and progress photos to fulfill our promises to the community.
Check out some pictures of our future plans and recent progress!







2021 Referendum Video
Recent Updates
-
November 2022
Nov. 17, 2022
On Nov, 17, Big Lake School board awarded the bids for the next phase in our multi-year plan. The following projects will begin in June of 2023:Big Lake High School: General Contractor KUE Contractor- Remodeling of the Media Center to create a 21st Century space for Innovation (projected to open Fall 2023)
- Creating an all-new Fitness Center in the current district office space (projected to open Spring 2024)
Independence STEM Elementary - General Contractor Ebert Construction- Remodeling the Media Center to further support STEM and literacy
- Creating new STEM support spaces
- Updating ventilation systems and replacing aging finishes and fixtures (lighting, flooring, cabinets and visual display boards) in the 1980´s portion of the building.
Note: Independence STEM Elementary renovations will be a multi-year project due to the size and scope of the project.Materials and Renderings UpdatesThese presentations provide images of 3D renderings of the new facilities and outline the materials that will be used. -
March 2021
March 25
March 17
March 11
More Information
-
Timeline/Progress
Liberty Elementary Projects
Project
Timeline
Notes
Roof Replacement
Completed
Bid awarded to Palmer West Construction in the amount of $2,236,700.
NAC Mechanical and Electrical awarded bid of $346,750 for disconnect and reconnect of all mechanical and electrical equipment.
Building Control System Replacement September 2022-July 2023 Media Center Improvements
Summer of 2025
Parking Lot Improvements
Summer of 2025
Flexible Learning Spaces Additions
Summer of 2025
Professional fees, contingency costs and furniture, fixtures and equipment
Independence Elementary STEM Projects
Project
Scheduled Start Date
Notes
--Addition of Flexible Learning Spaces
--Relocation of District Office to Independence
--Building Control System Replacement
--Media Center Improvements
--HVAC System Replacement
--Contemporary amenities added in renovated areas
June 2023-September 2024
Contract Awarded to Ebert Construction $10,417,100
Renovations will be a multi-year project due to the size and scope of the project.
Replacements and Renovations to 1997 Addition (Updating ventilation systems and replacing aging finishes and fixtures)
June 2025-August 2025
Professional fees, contingency costs and furniture, fixtures and equipment
Middle School Projects
Project
Scheduled Start Date
Notes
Roof Replacement
June 2022-Jan 2023
Bid awarded to McDowall Company in the amount of $674,700.
Signature Mechanical awarded bid of $25,000 for disconnect and reconnect of all mechanical and electrical equipment.
Media Center Improvements
Summer 2025
Improve Special Education Areas
Summer 2025
Flexible Learning Spaces Additions
Summer 2025
Add contemporary amenities, technology, and equipment in renovated areas.
Summer 2025
CTE and Future Ready Environment Improvements
Summer 2025
Professional fees, contingency costs and furniture, fixtures and equipment
High School Projects
Project
Scheduled Start Date
Notes
Roof Replacement
Completed
Bid awarded to B.L. Dalsin Roofing in the amount of $1,031,745.
McDowall Company awarded bid in the amount of $98,890 for disconnect and reconnect of all mechanical and electrical equipment.
Air Conditioning/Air Quality Improvements
May 2022-October 2022
Bid awarded to Northern Air Corporation in the amount of $1,427,623.
Building Controls Improvements
May 2022-Jan 2023
-- Improvements to media center and CTE/ Future Ready Environments
--Addition of Flexible Learning Spaces and a new fitness center
--Contemporary amenities added in renovated areas
Spring/Summer 2023
Project awarded to Kue Construction for $2,988,003
Media Center Projected Opening: Fall 2023
Fitness Center Projected Opening: Spring 2024
Professional fees, contingency costs and furniture, fixtures and equipment
-
Project List
Media Center Improvements (all buildings): The media centers in all 4 buildings will be improved to meet 21st Century learning needs. Spaces will contain multi-purpose rooms, maker spaces, areas for groups of all sizes, and include high-density storage where appropriate. The new spaces will include right-size quantity of book stacks per grade level(s) and should account for 1:1 devices and repurpose computer labs where appropriate. Spaces will contain contemporary amenities, technology, and equipment.
Flexible Learning Spaces Additions (all buildings): New spaces will be added in all 4 buildings for independent, flexible, and personalized learning, including space for students in-between classes and when online learners are in-person. Spaces will contain contemporary amenities, technology, and equipment.
Roof Replacements (Liberty, Middle School, High School): The roofs at Liberty, the Middle School, and the High School, which are past their life cycles and are in poor physical condition, will be replaced.
Building Control System Replacements (Liberty, Independence, High School): The outdated and difficult to maintain building control systems at Liberty, Independence, and the High School will be replaced.
District Office Relocation/New High School Fitness Center: The district office will be moved to Independence Elementary STEM. The current district office will be made into a new fitness center/weight room with contemporary amenities and equipment.
New and Improved CTE and Future Ready Environments (Middle School & High School) New spaces focused on CTE will be added at the High School and Middle School. These areas will contain multi-purpose spaces with emphasis on collaboration and flexibility. The spaces will reflect the current market needs to better prepare students. Renovations would include separate ‘clean’ and ‘dirty’ work areas, contain contemporary amenities, technology, and equipment, be more open, and be handicap accessible for all.
Added Parking at Liberty: The parking lot at Liberty will be renovated to improve efficiency, safety, traffic flow. More parking stalls will be added to the existing parking lot.
New HVAC at Independence Elementary STEM: The 1981 HVAC system at Independence Elementary STEM is in need of replacement. This replacement would include a better air quality handling system as well as air conditioning.
Improved Special Education Areas at the Middle School: These spaces are being reconfigured to operate more efficiently and designed to meet program needs. Learning environments (lights & HVAC) will be improved and equitable across all buildings. The spaces will be right-sized per MDE guidelines and contain their own dedicated storage areas. Materials and finishes in poor physical condition would be replaced. Spaces will contain contemporary amenities, technology, and equipment.
Air Conditioning and Air Quality Improvements (High School): Air conditioning will be added and systems will be put in place to improve indoor air quality in activity spaces at the high school.
-
Frequently Asked Questions About the Bond Referendum
Why were these projects not on the 2016 Referendum?
The last bond referendum passed in 2016 was primarily focused on improving safety and security including updating surveillance cameras and remodeling building entrances: expanding an improving playgrounds; as well as improving fine arts and athletic facility improvements such as replacing auditorium equipment, pool equipment, adding permanent outdoor concession/restroom facilities, and installing ball field lighting.
All school funding measures that are voted on by the public are community-driven. At the time in 2016, input from our community was focused on our district providing security for our students, updating our fine arts facilities (like the auditorium) and improving our outdoor recreational spaces.
How is the referendum a $0 tax increase?
The debt from the voter approved bond referendum that financed the construction of Liberty Elementary School (along with additions to the High School and Middle School, and improvements to Independence Elementary School), will be paid off on February 1, 2022. In partnership with community groups, we identified important facility infrastructure projects that need to be completed in the upcoming years to restore and renew our current facilities. As part of the criteria for these infrastructure projects, the need to keep our tax rate level was of the utmost importance.
Aren't the High School activity spaces already air conditioned?
High School activity spaces including the main gym and auxillary gymnastics gym are not air conditioned and in need of dehumidifcation during peak use including the spring, summer, and fall time.
What does it mean that "building controls" are no longer supported?
HVAC and building controls across the district are 24 years old. The computer systems they operate on are no longer able to support the aging control panels.
Where will the High School fitness center be located?
The current plan is for the High School fitness center to be relocated where the District Office currently is. The District Office would be relocated to Independence Elementary.
What roofs need to be replaced?
When constructed in 2002, Liberty Elementary had a roof with a 15 year life span installed. The roof is now 18 years old and in need of replacement. Additionally, portions of the Middle School roof including the 1987 and 2001 addition need replacing.
How old is the HVAC system at Independence Elementary?
The HVAC system at Independence Elementary was installed in 1981 and is in need of replacement. This replacement would include a better air quality handling system as well as air conditioning.
Will this referendum add square footage to our buildings?
This referendum will restore and renew existing facilities. It will not add square footage to any of our buildings.
-
Fast Facts about the Bond Referendum
It is important to be good stewards of the community's schools. Given the age of the buildings - it was time to make further investments into Big Lake Schools.
The last major investment in facilities was in 2016, and was primarily focused on improving safety and security, including updating surveillance cameras and remodeling entrances; expanding and improving playgrounds; as well as improving fine arts and athletic facility improvements, such as replacing auditorium equipment, pool equipment, adding permanent outdoor concession/restroom facilities, and installing ball field lighting.
- When constructed in 2002, Liberty Elementary had a roof with a 15 year life span installed. The roof is now 19 years old and in need of replacement.
- Portions of the Middle School roof, including the 1987 and 2001 additions, need replacing.
- The 1981 HVAC system at Independence Elementary STEM is in need of replacement. This replacement would include better air quality handling systems as well as air conditioning.
- High School activity spaces including the main gym and auxiliary gymnastics gym are not air conditioned and in need of dehumidification during peak use including the spring, summer, and fall time.
- Special Education spaces at the Middle School were constructed in 1997 and are in need of redesign.
- HVAC and building controls across the district are 24 years old. The computer systems they operate on are no longer able to support the aging control panels.